Cambridge University Estate Management and Building Service
Architect
Edward Cullinan Architects
Main Contractor
John Laing Construction
Alumasc Approved Specialist Sub-Contractor
Briggs Roofing & Cladding
Type of Development
University Building / Maths Facility
Reason for Green Roof
Type of Roof
Intensive Green Roof
Size of Green Roof
a total 1200m2
Build up of Roof
The roof comprises a Hydrotech waterproofing system with root barrier, Top-foam extruded polystyrene insulation systems and a Floradrain FS100 drainage layer specially designed for use on pitched green roofs. Alumasc also supplied the 200mm-deep layer of intensive soil and turf.
Comments
The building will eventually comprise seven satellite ‘pavilions’ linked to central building via pathway bridges.